Content
1.2 Construction Works Programme
1.4 License, Notification and Permits
1.5 Brief Summary of EM&A Requirements
2.2 Air Quality Monitoring
Parameter, Frequency and Duration
2.3 Monitoring Equipment and
Methodology and QA/ QC Procedure
3.2 Noise Monitoring
Parameter, Frequency and Duration
3.3 Monitoring Equipment,
Methodology and QA / QC Procedure
3.4 Maintenance and
Calibration
5. environmental site inspection and audit
6. environmental non-compliance
6.2 Summary of Environmental
Non-Compliance
6.3 Summary of Environmental Complaint
6.4 Summary of Environmental Summon
and Successful Prosecution
7.1 Construction Works and
Potential Environmental Issues in the next Reporting Period
8. ConclUsion, Comments and recommendation
8.2 Comments and Recommendations
List of Tables
Table I Summary
of EM&A Activities in the Reporting Period
Table II Summary
of Exceedance in the Reporting Period
Table 1.1 Status
of Environmental License, Notification and Permits
Table 1.2 Summary of Status of Submission under EP-602/2021
Table 2.1 Air
Quality Monitoring Stations for Construction Phase
Table 2.2 Impact
Air Quality Monitoring Parameter, Duration and Frequency
Table 2.3 Impact
Air Quality Monitoring Equipment
Table 2.4 Action
and Limit Levels for 1-hour TSP
Table 2.5 Summary
of Impact 1-hour TSP Monitoring Results
Table 2.6 Influencing
Factors at / near Air Quality Monitoring Stations
Table 3.1 Noise
Monitoring Stations during Construction Phase
Table 3.2 Construction
Noise Monitoring Parameter, Frequency and Duration
Table 3.3 Construction
Noise Monitoring Equipment
Table 3.4 Action
and Limit Levels for Construction Noise Monitoring
Table 3.5 Summary
of Construction Noise Monitoring Results
Table 3.6 Influencing
Factors at Noise Monitoring Stations
Table 4.1 Summary
of Waste Generated in the Reporting Period
Table
5.1 Summary of Site
Inspections Observation and Recommendations
List of Figure
Figure 1.1 Project
Layout Plan
Figure 2.1 Air
Quality Monitoring Stations
Figure 3.1 Construction
Noise Monitoring Stations
List of Appendices
Appendix A Master
Construction Programme for the Project
Appendix B Project
Organization Chart and Key Personnel Contact
Appendix C Event
and Action Plans
Appendix D Project
Implementation Schedule
Appendix E Air
Quality and Noise Monitoring Equipment Calibration Certification
Appendix F Environmental
Monitoring Schedule
Appendix G Air
Quality Monitoring Results and Graphical Presentation
Appendix H Extract
of Meteorological Observations for Hong Kong (Kai Tak)
Appendix I Noise
Monitoring Results and Graphical Presentation
Appendix J Waste
Generation in the Reporting Month
Appendix K Summary
of Complaint, Notification of Summons and Prosecution and Cumulative Complaint
Log
This is the 4th Monthly Environment
Monitoring and Audit (EM&A) Report for Relocation of Diamon Hill Fresh
Water and Salt Water Service Reservoirs to Caverns (the Project). This report
was prepared by Acuity Sustainability Consulting Limited under Contract No.
21/WSD/21 (hereafter called “the Contract”). This report documents the findings of EM&A
works during the reporting period from 1 July to 31 July 2023.
Key Construction Works in the Reporting Period
A summary of construction activities undertaken
during the reporting period is presented below:
·
Site formation;
·
Pipe piling;
·
Tree transplanting;
·
Hoarding erection; and
·
Temporary traffic Arrangement (TTA) site setup works.
Environmental Monitoring and Audit Programme
The monthly EM&A programme was undertaken by the
Environmental Team in accordance with the EM&A Manual. A summary of the
monitoring and audit activities during the reporting period is presented below:
Table
I Summary of EM&A
Activities in the Reporting Period
EM&A Activities |
Date |
1-hour TSP Monitoring |
5, 11, 19, 22 and 28 July 2023 |
Construction Noise Monitoring |
5, 11, 22 and 28 July 2023 |
Weekly Environmental Site Inspection |
7, 14, 21 and 26 July 2023 |
Breaches of Action and Limit Levels
A summary of the environmental monitoring exceedance
of the reporting period is tabulated in Table
II.
Table
II Summary of Exceedance in the
Reporting Period
Environmental Monitoring |
Parameter |
No. of non-project related exceedances |
Total no. of non-project related
exceedances |
No. of exceedances related to the project |
Total no. of exceedances related to the
project |
||
AL |
LL |
AL |
LL |
||||
Air Quality |
1-hour TSP |
0 |
0 |
0 |
0 |
0 |
0 |
Noise |
Leq(30-min) |
0 |
0 |
0 |
0 |
0 |
0 |
Air Quality
No action or limit levels exceedance was recorded
for 1-hour TSP monitoring during the reporting period.
Construction Noise
No action or limit levels exceedance was recorded
for construction noise monitoring during the reporting period.
Complaint Log
No environmental complaint was received in the
reporting period.
Notification of Summons and Successful Prosecutions
No notification of summons or successful
prosecutions was received in the reporting period.
Reporting Change
There was no reporting change in the reporting
period.
Future Key Issues
Key issues to be considered in the next two months
included:
·
Open trench for mainlaying
and Mainlaying;
·
Jacking pit construction for pipe jacking
·
Trial pit excavation;
·
Formation of piling platform at +89.0mPD;
·
Pipe piling for PAB ELS wall;
·
Site compound set up;
·
ELS works in Portion 3; and
·
Canopy table installation in Portion 3.
Potential environmental impacts arising from the
above construction activities are mainly associated with construction dust,
construction noise, water pollution control, waste management and landscape and
visual.
1.1.1
The relocated Diamond Hill Fresh Water and Salt
Water Service Reservoirs (DHSRs) will be constructed in a series of caverns
linked by access tunnels and adits. The relocated
Diamond Hill Fresh Water Service Reservoirs (DHFWSR) and Diamond Hill Salt
Water Service Reservoirs (DHSWSR) will be compartmented while the existing Diamond
Hill Pumping Station (DHPS) will be split into two (2) pump houses for fresh
and salt water supply when relocated.
1.1.2
Ancillary facilities to be constructed near the
tunnel portal may include transformer room, switch room, emergency generator
room, control room, ventilation building, and pumping station control room,
which will be constructed in an above-ground building outside the tunnel.
1.1.3
The scope of the Project comprises the following:
a)
Construction of the relocated DHSRs and associated
pumping stations and water main laying works;
b)
Construction of tunnels, adits,
ventilation system and caverns for accommodating the relocated DHSRs and the
associated facilities;
c)
Terminating the operation of the existing DHSRs and
the associated facilities; and
d)
All other associated works that are incidental to
and necessary for the completion of the Project.
1.1.4
The major construction activities of the Project
include earthworks, drilling and blasting, construction of concrete structures,
handling and transportation of excavated materials, water mains laying,
installation of electrical and mechanical (E&M) equipment and material
transportation. The operation of the
existing DHSRs and the associated facilities will be terminated after the
completion of the testing and commissioning of the relocated DHSRs. Under the Project, the existing DHSRs and
associated facilities will be retained after termination of the operation. The subsequent demolition works will be carried
out by other government departments/ project proponents.
1.1.5
The Project construction was commenced on 31 March
2023 and the completion date for the construction works would be on 12 April
2027.
1.1.6
The Project is a Designated Project under Item Q.2, Part
I of Schedule 2 of the Environmental Impact Assessment Ordinance,
"Underground Rock Caverns", which requires an environmental permit
from Environmental Protection Department for its construction and operation.
1.1.7
Pursuant to the Environmental Impact Assessment
Ordinance (EIAO), the Director of Environmental Protection Department (EPD)
granted the Environmental Permits (EP-602/2021) to the Water Supplies
Department (WSD) for the Project.
1.1.8
Acuity Sustainability Consulting Limited (ASCL) is
commissioned by Chun Wo – Sinohydro Joint Venture to
undertake the role of Environmental Team under the Environmental Permit (EP)
EP-602/2021, and to carry out the EM&A programme in fulfilment of the
EM&A Manual, and other requirements stipulated in the associated EIA Report.
1.1.9
This is the 4th Monthly
EM&A Report summarizing the key findings of the construction phase EM&A
programme from 1 July to 31 July 2023 (the reporting period) and is submitted
to fulfil the requirements in Conditions 3.4 of EP-602/2021 and section 13.3 of
the EM&A Manual of the Project.
1.2.1
The construction works of the Project was commenced
on 31 March 2023. The construction works
programme, and the location of construction works of the Project are shown in Appendix
A
and Figure 1.1, respectively. A summary of
construction activities undertaken during the reporting period is presented
below:
·
Site formation;
·
Pipe piling;
·
Tree transplanting;
·
Hoarding erection; and
·
TTA site setup works.
1.3.1
Different parties with different levels of
involvement in the Project organization include:
·
Project Proponent: Water Supplies Department (WSD)
·
Supervisor/Engineer’s Representative (ER): Binnies
Hong Kong Limited
·
Contractor: Chun Wo - Sinohydro
Joint Venture
·
Environmental Team (ET): Acuity Sustainability
Consulting Limited
·
Independent Environmental Checker (IEC): Umwelt
Consulting Limited
1.3.2
The key personnel contact names and telephone number
are presented in Appendix B.
1.4.1
A summary of the relevant permit, licences, and/ or
notifications on environmental protection for this Project are presented in Table
1.1.
Table 1.1 Status of Environmental License,
Notifications and Permits
Permit
/ License No. |
Valid
Period |
Status |
|
From
|
Expired
On |
||
Environmental Permit |
|||
EP-602/2021 |
14/12/2021 |
- |
Valid |
Notification Pursuant to Section 3(1) of the Air Pollution Control
(Construction Dust) Regulation |
|||
Ref. No.: 487301 |
09/12/2022 |
- |
Valid |
Billing
Account for Disposal of Construction Waste |
|||
7046085 |
04/01/2023 |
- |
Valid |
Registration
of Chemical Waste Producer |
|||
WPN 5213-282-C4760-0 |
30/12/2022 |
- |
Valid |
Effluent
Discharge License under Water Pollution Control Ordinance |
|||
WT00043965-2023 |
31/05/2023 |
31/05/2028 |
Valid |
Construction
Noise Permit |
|||
GW-RE0570-23 |
01/06/2023 |
31/08/2023 |
Valid |
1.4.2
The submission status of the EP and the
implementation status of the mitigation measures stated in the EP had been
reviewed, all submission were submitted/ deposited to the Director of
Environmental Protection (DEP) on schedule, no non-compliance of EP conditions
was recorded during the reporting period. The summary of submission status
under Environmental Permit EP-602/2021 are summarized in Table
1.2.
Table
1.2 Summary of Status of Submission under
EP-602/2021
EP Condition |
Title of Submission |
Submission Status |
1.11 |
Commencement Date of Construction |
Notified the
DEP on 22 Feb 2023 |
2.9 |
Management Organization(s) |
Informed the
DEP on 20 Feb 2023 |
2.10 |
Environmental Permit (EP) Submission Schedule |
22 Feb 2022
(1st Submission) |
2.11 |
Construction Works Schedule and Location Plan |
28 Feb 2023
(Deposited) |
2.12 |
Construction Noise Management Plan (CNMP) |
·
28 Feb 2023 (1st submission) ·
EPD’s comments were issued on 8 Mar 2023 ·
The revised CNMP was submitted to the EPD for comment on 31 July 2023. |
2.13 |
Waste Management Plan (WMP) |
· 28 Feb
2023 (1st submission) · EPD’s comments
were issued on 3 Apr 2023. · The revised
WMP was submitted to the EPD for comment on 26 July 2023. |
2.14 |
Landscape and Visual Mitigation Plan (LVMP) |
·
28 Feb 2022 (1st Submission) ·
EPD’s comments were issued on 29 Mar 2023 and the LVMP is being
revised. |
3.3 |
Baseline Monitoring Report |
· 17 Mar
2023 (1st Submission) · 27 Apr
2023 (2nd Submission) ·
1 June 2023 (3rd
Submission) · 13
July 2023 (Formal submission) |
3.4 |
Monthly EM&A Report (Apr 2023) |
15 May 2023 |
3.4 |
Monthly EM&A Report (May 2023) |
12 June 2023 |
3.4 |
Monthly EM&A Report (June 2023) |
13 July 2023 |
4.2 |
Dedicated Internet Website |
2 May 2023 |
1.4.3
Following the EPD’s comments on the Baseline Monitoring
Report (Ref. No. BMR-3.1, dated 17 March 2023), updating of air quality and
noise monitoring locations were proposed, including cancellation of noise
monitoring station at Tower 1, Meridian Hill (NM-1), resumption of air quality and noise
monitoring stations at Block 6, Tsui Chuk Garden (i.e. DM-4 and NM-4) and
proposal of new noise monitoring locations at Wo Tin House, Shatin Pass
Estate (NM-5) and Sheung Fung Street Customs Staff Quarter (NM-6).
1.4.4
Additional baseline monitoring for air quality
monitoring station DM-4, and noise monitoring stations NM-4, NM-5 and NM-6 was
carried out between 2 May and 16 May 2023. The Baseline Monitoring Report was
updated with all baseline monitoring results included, certified by the ET
Leader, and verified by the IEC on 30 May 2023. The updated Baseline Monitoring Report was
submitted to the EPD on 1 June 2023. A
minor comment was received from the EPD on 26 June 2023. Following the advice from the EPD, the Report
was formally submitted to the EPD on 13 July 2023 after amendment.
Air Quality
1.5.1
In accordance with the EM&A Manual, the ET shall carry out impact
monitoring during construction phase of the project. For 1-hour Total Suspended Particulates (TSP)
monitoring, the sampling frequency of at least three times every six days
should be undertaken when the highest dust impact occurs.
1.5.2
Action and Limit Levels for the 1-hour TSP monitoring works are discussed
in Section
2.4. Should non-compliance of the criteria occur,
action in accordance with the Event and Action Plan presented in Appendix C shall be carried out.
1.5.3
The air quality mitigation measures
detailed in the EM&A Manual were recommended to be implemented during the
construction phase. The implementation
statuses of these measures are presented in Appendix D.
Noise Monitoring
1.5.4
Construction noise monitoring should be carried out at the designated
monitoring stations directly affected by the construction works once every week
after the commencement of construction. During construction works, one set of Leq(30-min) measurement at
each station between 0700 and 1900 hours on normal weekdays shall be taken. If
construction works are extended to include works during the period between 1900
and 0700 hours, additional weekly impact monitoring shall be carried out during
evening and night-time works.
1.5.5
Action and Limit Levels for the noise monitoring are discussed in Section 3.5. Should non-compliance of the criteria occur,
action in accordance with the Event and Action Plan presented in Appendix C shall be carried out.
1.5.6
The noise mitigation measures detailed in
the EM&A Manual are recommended to be implemented during the construction
phase. The implementation statuses of
these measures are presented in Appendix D.
Environmental Requirements in Contract Documents
1.5.7
According to Particular Specification (PS), the Contractor
shall undertake environmental protection measures to reduce the environmental
impacts arising from the execution of the works. The Contractor shall also observe and comply
with relevant environmental protection and pollution control ordinances. The Contractor shall design, construct,
operate and maintain pollution control measures to ensure compliance with the
contract provisions as well as the environmental ordinances and their
regulations.
1.5.8
The Contractor shall also:
·
Implement air pollution and noise abatement practices as specified in PS;
·
Minimise generation of wastewater from the Site;
·
On-site sorting of Construction and Demolition (C&D) Materials;
·
Establish a mechanism to record the quantities of C&D materials
generated each month, using the monthly summary “Waste Flow Table”;
·
Control the use of timbers;
·
Implement a trip ticket system (TTS) for tracking the removal of C&D
materials from the Site to the disposal grounds;
·
Prepare an Environmental Management Plan (EMP) in accordance with GS
Section 25 and PS for implementation on the Site to reduce environmental
nuisance and C&D materials arising from Works, throughout the construction
period;
·
Arrange weekly environmental walk to inspect the Site, checking that the
environmental performance of the Site is satisfactory and in compliance with
the requirements under the contract and EMP; and
·
Carry out site specific induction training about environmental management
as well as safety for all staffs and workers, and provide toolbox talks for
workers on environmental nuisance abatement and waste management.
2.1.1
The air quality monitoring locations for impact monitoring during the
reporting period are listed in Table
2.1 and presented
in Figure
2.1.
Table 2.1 Air
Quality Monitoring Stations for Construction Phase
ID |
Description |
Coordinates |
|
Northing |
Easting |
||
DM-1 |
Tennis
Court near Tin Ma Court |
822705 |
837047 |
DM-2 |
Chun
Sing House, Tin Ma Court |
822673 |
837143 |
DM-3 |
Grace
Methodist Church Kindergarten |
822782 |
837227 |
DM-4 (1) |
Block
6, Tsui Chuk Garden |
822926 |
837246 |
DM-4a (2) |
Road pavement near Wang King House, Tin Wang Court |
822854 |
837340 |
Notes:
1.
Following the EPD’s
comment on the Baseline Monitoring Report (Ref. No. BRM-3.1, dated 17 March
2023), air quality monitoring at DM-4 was resumed. Baseline monitoring for air quality monitoring
station DM-4 was then carried out between 2 May and 16 May 2023. Impact monitoring at DM-4 was commenced on 22
May 2023.
2.
An additional air quality
monitoring station DM-4a was proposed by the ET and agreed by the ER, IEC and
EPD.
2.2.1
Table 2.2 summarized the monitoring
parameter, duration, and frequency of impact air quality monitoring.
Table 2.2 Impact
Air Quality Monitoring Parameter, Duration and Frequency
Parameter |
Frequency |
Duration |
1-hour TSP |
3 times every 6 days |
Throughout the
construction phase |
Proposal of Using Portable Direct Reading Dust Meter
2.3.1
Direct reading dust meters were used for measuring 1-hour TSP levels
during the impact air quality monitoring. According to Section 4.4.1 of the EM&A
Manual, the proposed use of direct reading dust meters was submitted to and
agreed by the IEC.
2.3.2
Sufficient number of monitoring instruments were prepared by the ET for
carrying out the impact monitoring. All
equipment and associated instrumentation were clearly labelled.
2.3.3
Wind
data were collected from the records of Hong Kong Observatory Kai Tak Wind
Station (22.30966N,
114.21336E), which is located at the south-eastern side of
runway of the former Kai Tak Airport about 4.5 km south-east from the project
site.
2.3.4
Equipment used in the impact air quality monitoring programme is
summarised in Table
2.3. Calibration certificates for the impact air
quality monitoring equipment are attached in Appendix E.
Table
2.3 Impact Air Quality Monitoring
Equipment
Equipment |
Brand and Model |
Serial No. |
Calibration Due Date |
Direct Reading Dust Meter |
Sibata LD-5R |
0Z4545 |
29/02/2024 |
882106 |
29/02/2023 |
||
942532 |
29/02/2024 |
Maintenance and Calibration
2.3.5
Direct reading dust meters have been calibrated against high volume
samplers (HVSs) annually. A 2-day, three
3-hour measurement results per day from direct reading dust meters were taken
to compare with the sampling results from the HVSs. The correlation between the direct reading
dust meters and the HVSs were then concluded.
By accounting for the correlation factor, the direct reading dust meters
are considered to achieve comparable results as that of the HVSs.
2.3.6
The 1-hour TSP measurement follows the instruction provided in the
manufacturer's manual. Before initiating
a measurement, zeroing the portable dust meter was carried out to ensure the
accuracy of each measurement.
2.4.1
The action and limit levels were established in accordance with the
EM&A Manual. Table
2.4 presents the
action and limits levels for 1-hour TSP monitoring. Should non-compliance of the criteria occur,
action in accordance with the Event and Action Plan presented in Appendix C shall be carried out.
Table 2.4 Action
and Limit Levels for 1-hour TSP
Monitoring
Station |
Action
Level (µg/m3) |
Limit Level (µg/m3) |
DM-1 |
300.1 |
500 |
DM-2 |
289.0 |
|
DM-3 |
289.7 |
|
DM-4 |
294.9 |
|
DM-4a |
291.6 |
2.5.1
The impact air quality monitoring was conducted on 5,
11, 19, 22 and 28 July 2023. The impact air quality monitoring scheduled on 17
July 2023 was cancelled due to adverse weather and was rescheduled on 19 July
2023. The impact air quality monitoring schedule for the reporting period is
shown in Appendix
F.
2.5.2
The monitoring results and graphical presentation of impact air quality
monitoring are shown in Appendix
G. No action or limit levels exceedance was
recorded in the reporting period.
Table 2.5 Summary of Impact 1-hour TSP Monitoring
Results
Monitoring
Station |
TSP
Concentration, μg/m3 |
Action Level |
Limit Level |
||
Average |
Minimum |
Maximum |
|||
DM-1 |
58 |
55 |
62 |
300.1 |
500 |
DM-2 |
59 |
52 |
63 |
289.0 |
|
DM-3 |
56 |
49 |
59 |
289.7 |
|
DM-4 (1) |
54 |
42 |
63 |
294.9 |
|
DM-4a |
60 |
56 |
63 |
291.6 |
Remark: (1) Impact
air quality monitoring at DM-4 was commenced on 22 May 2023.
2.5.3
During the impact air quality monitoring, the major dust sources at each
monitoring stations were summarized in Table 2.6.
Table 2.6 Influencing
Factors at / near Air Quality Monitoring Stations
Monitoring
Stations |
Influencing
Factors |
DM-1 |
Not identified |
DM-2 |
Not identified |
DM-3 |
Not identified |
DM-4 |
Not identified |
DM-4a |
Not identified |
2.5.4
Weather conditions during impact monitoring are presented in Appendix G and extracts of wind data recorded at Kai Tak Wind
Station available from the Hong Kong Observatory are presented in Appendix H.
3.1.1
The monitoring locations for construction noise monitoring
are listed in Table 3.1 and shown in Figure 3.1.
Table 3.1 Noise
Monitoring Stations during Construction Phase
ID |
Description |
Measurement |
Coordinates |
|
Northing |
Easting |
|||
NM-2 |
Chun
Sing House, Tin Ma Court |
Façade |
822668 |
837143 |
NM-3 |
Grace
Methodist Church Kindergarten |
Façade |
822782 |
837227 |
NM-4 (2) |
Block
6, Tsui Chuk Garden |
Façade |
822926 |
837246 |
NM-4a (1) |
Road pavement near Wang King House, Tin Wang Court |
Free field |
822854 |
837340 |
NM-5 |
Wo Tin House, Shatin Pass Estate |
Façade |
823360 |
838143 |
NM-6 |
Sheung Fung Street Customs Staff Quarters |
Free field |
823134 |
838412 |
Notes:
The noise
monitoring station proposed in the EM&A Manual (NM-1) was not available for
baseline and impact monitoring. Therefore,
impact monitoring at NM-1 was cancelled and agreed by the ER, IEC and EPD.
(1) An additional noise monitoring station NM-4a
was proposed by the ET and agreed by the ER, IEC and EPD.
(2) Following the EPD’s comment on the Baseline
Monitoring Report (Ref. No. BRM-3.1, dated 17 March 2023), noise monitoring
station was resumed at NM-4. Baseline
monitoring for noise monitoring station NM-4 was then carried out between 2 May
and 16 May 2023. Impact monitoring at
NM-4 was commenced on 22 May 2023.
3.1.2
No construction work was conducted within 300m
radius of noise monitoring station NM-5 and NM-6. Thus, no construction noise
monitoring was carried out at these two noise monitoring stations in the
reporting period.
3.2.1
Construction noise level was measured by the ET and measured in terms of
the A-weighted equivalent continuous sound pressure level (Leq). Leq(30-min)
was adopted as the monitoring parameter for the construction noise
monitoring.
3.2.2
As supplementary information for data auditing, statistical results such
as L10 and L90 were also obtained for
reference.
3.2.3
Table
3.2 summarized the monitoring parameters, duration, and
frequency of construction noise monitoring.
Table 3.2 Construction Noise Monitoring Parameter,
Frequency and Duration
Parameters |
Time |
Frequency |
Duration |
Leq(30-min) |
0700 and 1900 hours on normal weekdays |
once every week |
Throughout the
construction phase |
3.3.1
As referred to the technical memorandum (TM) issued under the NCO, sound
level meters in compliance with the International Electrotechnical Commission
Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications were used
for carrying out the construction noise monitoring.
3.3.2
Noise measurements were not made in fog, rain, wind with a steady speed
exceeding 5 m/s or wind with gusts exceeding 10 m/s. The wind speed was checked with a portable
wind speed meter capable of measuring the wind speed in m/s.
3.3.3
Sufficient numbers of noise measuring equipment and associated
instrumentation were prepared by the Environmental Team. All the equipment and associated
instrumentation were clearly labelled.
3.3.4
Wind
data were collected from the records of Hong Kong Observatory Kai Tak Wind
Station (22.30966N,
114.21336E), which is located at the south-eastern side of
runway of the former Kai Tak Airport about 4.5 km south-east from the project
site.
3.3.5
The monitoring procedures are as follows:
·
For façade measurement, the monitoring station was set at a point 1 m
from the exterior of the sensitive receivers building façade and set at a
position 1.2 m above the ground. For
free-field measurement, the monitoring station was set at a position 1.2 m above the ground.
·
The battery condition was checked to
ensure good functioning of the meter.
·
Parameters such as frequency weighting,
the time weighting and the interval were set as follows:
·
Frequency weighting: A
·
Time weighting : Fast
·
Interval :
30 minutes (Leq(30-min))
would be determined for daytime
noise
by calculating the logarithmic average of six Leq(5-min)
data
·
Prior to and after each noise measurement, the meter was calibrated using
an acoustic calibrator for 94.0 dB at 1000 Hz. If the difference in the calibration level
before and after measurement is more than 1.0 dB, the measurement was
considered invalid and repeat of noise measurement will be required after
re-calibration or repair of the equipment.
·
At the end of the monitoring period, the values of Leq,
L90 and L10 were recorded. In addition, noise sources were recorded on a
standard record sheet.
3.3.6
Table
3.3 summarized the
noise monitoring equipment used during the construction noise monitoring. Calibration certificates for the impact noise
monitoring equipment are attached in Appendix E.
Table
3.3 Construction Noise Monitoring
Equipment
Equipment |
Model (Serial Number) |
Calibration Due Date |
Sound Level Meter |
Nti-XL2 (A2A-13548-E0) |
05/02/2024 |
Nti-XL2 (A2A-13661-E0) |
21/08/2023 |
|
Sound Calibrator |
Rion NC 75 (35124529) |
01/11/2023 |
3.4.1
Maintenance and calibration procedures are as follows:
·
The microphone head of the sound level meter and calibrator were regularly
cleaned with a soft cloth; and
·
The sound level meter and acoustic calibrator were calibrated annually by
a HOKLAS accredited laboratory or the manufacturer.
3.5.1
The Action and Limit levels were established in accordance with the
EM&A Manual. Table
3.4 presents the
Action and Limit Levels for construction noise. Should non-compliance of the
criteria occur, action in accordance with the Event and Action Plan presented
in Appendix
C shall be
carried out.
Table 3.4 Action and Limit Levels for Construction
Noise Monitoring
Monitoring Stations |
Action
Level |
Limit
Level |
Time
Period |
NM-2 |
When
one documented complaint is received |
75
dB(A) |
0700
- 1900 hours on normal weekdays |
NM-3 |
70/
65 dB(A) * |
||
NM-4 |
75
dB(A) |
||
NM-4a |
75
dB(A) |
||
NM-5 |
75
dB(A) |
||
NM-6 |
75
dB(A) |
Notes:
If works
are to be carried out during restricted hours, the conditions stipulated in the
construction noise permit issued by the Noise Control Authority have to be
followed.
* Reduce to 70 dB(A) for schools and 65 dB(A)
during school examination periods.
3.6.1
The construction noise monitoring was conducted on 5,
11, 22 and 28 July 2023. The impact construction noise monitoring scheduled on
17 July 2023 was cancelled due to adverse weather. The monitoring schedule is presented in Appendix
F.
3.6.2
The construction noise monitoring results are summarized in Table 3.5. No Action
or Limit levels exceedance was recorded in the reporting period. Details of the results and graphical
presentation are shown in Appendix
I.
Table 3.5 Summary
of Construction Noise Monitoring Results
Monitoring Station (1) |
Noise Level, dB(A) |
Limit Level |
||
Leq(30-min) |
||||
Mean |
Minimum |
Maximum |
|
|
NM-2 |
67.4 |
59.7 |
70.1 |
75 dB(A) |
NM-3 |
66.8 |
63.8 |
68.8 |
70/ 65 dB(A) (2) |
NM-4 (3) |
66.4 |
64.7 |
67.4 |
75 dB(A) |
NM-4a |
73.4 |
71.7 |
75.0 |
75 dB(A) |
Note:
(1)
Construction
noise monitoring at NM-4 and NM-5 will commence when construction works are
undertaking near these stations.
(2)
Reduce to 70
dB(A) for schools and 65 dB(A) during school examination periods.
(3)
Impact
monitoring at NM-4 was commenced on 22 May 2023.
3.6.3
Weather conditions during impact monitoring are presented in Appendix I and extracts of wind data recorded at Kai Tak Wind
Station available from the Hong Kong Observatory are presented in Appendix H.
3.6.4
During the construction noise monitoring period, the influencing factors
which may affect the results are summarized in Table 3.6.
Table 3.6 Influencing
Factors at Noise Monitoring Stations
Monitoring
Stations |
Influencing
Factors |
NM-2 |
Road traffic noise, construction
noise from 76 Broadcast Drive project |
NM-3 |
Road Traffic Noise |
NM-4 |
Road Traffic Noise |
NM-4a |
Road Traffic Noise |
4.1.1
Waste generated from the Project includes inert construction and
demolition (C&D) materials and non-inert C&D wastes in the reporting
period. The amount of waste generated by the construction works of the Project
during the reporting period is shown in Table 4.1 and the cumulative waste flow table was presented
in Appendix
J.
Table 4.1 Summary
of Waste Generated in the Reporting Period
Month |
Actual Quantalities of Inert C&D
Materials Generated Monthly |
Actual Quantities of C&D Wastes
Generated Monthly |
Actual Quantities of C&D Wastes
Recycled |
|||||||||||||
Total Quantity Generated |
Broken Concrete (Including rock for recycling into
aggregates) |
Reused in the Contract |
Reused in other Projects |
Disposed as Public Fill |
Imported Fill |
Metals |
Paper / Carboard Packing |
Plastics |
Chemical Waste |
Others e.g., general refuse |
Metals |
Paper/ cardboard packaging |
Plastics (bottles/ containers, plastic
sheets/foam package material) |
Yard Waste |
Others |
|
(in ‘000m3) |
(in ‘000m3) |
(in ‘000m3) |
(in ‘000m3) |
(in ‘000m3) |
(in ‘000m3) |
(in ‘000kg) |
(in ‘000kg) |
(in ‘000kg) |
(in ‘000kg) |
(in ‘000m3) |
(in ‘000kg) |
(in ‘000kg) |
(in ‘000kg) |
(in ‘000kg) |
(in ‘000m3) |
|
Jul 2023 |
0.06719 |
0.00000 |
0.00000 |
0.00000 |
0.06719 |
0.00000 |
0.00000 |
0.00000 |
0.00000 |
0.00000 |
0.00618 |
0.00720 |
0.00335 |
0.00980 |
0.00000 |
0.00000 |
4.1.2
Construction and demolition (C&D) materials sorting was carried out
on site. Sufficient receptacles were
provided for general refuse collection and sorting. Excavated inert C&D materials were reused
to minimize the disposal of C&D waste to public fill.
4.1.3
The Contractor was advised to minimize the amount of waste through
recycling or reusing. All applicable
mitigation measures stipulated in the EM&A Manual and waste management
plans shall be fully implemented.
5.1.1
Site inspections were carried out by the
ET on a weekly basis to monitor the implementation of proper environmental
pollution control mitigation measures for the
Project. During the reporting period,
site inspections were carried out 7, 14, 21 and 26 July 2023. Joint site inspection with the ER, the
Contractor and the IEC was carried out on 14 July 2023.
5.1.2
During the site inspections in the
reporting period, no non-conformance was identified. Key observations and reminders during the site
inspections are described in Table 5.1.
Table
5.1 Summary of Site Inspection Observations
and Recommendations
Inspection
Date |
Key
Observation / Reminders |
Follow-up
Action |
7 Jul 2023 |
No major environmental deficiency
was observed. |
N/A |
14
Jul 2023 |
1. Chemical containers found within
the Material Storage Area near the site office building should be placed with
drip tray(s) underneath. (Lower Portion 3) (Observation) 2. Chemical containers found within
the site should be placed with drip tray(s) underneath. (Upper Portion 3)
(Observation) |
1. Chemical containers were removed
on the same day. 2. Chemical containers were removed
on the same day. |
21
Jul 2023 |
No major environmental deficiency
was observed. |
N/A |
26
Jul 2023 |
1. Stockpile of dusty materials shall
be covered with tarpaulin to prevent dust emission. (Reminder) |
1. Stockpile of dusty materials was
covered with tarpaulin. |
5.1.3
According to the EIA Report, EP and the
EM&A Manual, the mitigation measures detailed in the documents are
recommended to be implemented during the construction phase. A summary of the Project Implementation
Schedule is provided in Appendix D.
6.1.1
No Action Level or Limit Level exceedance was recorded for 1-hour TSP
monitoring in the reporting period.
6.1.2
No Action Level or Limit Level exceedance was recorded for construction
noise monitoring in the reporting period.
6.1.3
Should the monitoring results of the
environmental monitoring parameters at any designated monitoring stations
indicate that the Action/ Limit Levels are exceeded, the actions in accordance
with the Event and Action Plans in Appendix C would be carried out.
6.2.1
No environmental non-compliance was recorded in the reporting period.
6.3.1
No environmental complaint was received in the reporting period. The Cumulative Complaint Log is presented in Appendix K.
6.4.1
There was no successful environmental prosecution or notification of
summons received since the Project commencement. The Cumulative Log for environmental summon
and successful prosecution is presented in Appendix K.
7.1.1
The construction programme for the Project
for the next reporting period is presented in Appendix A.
7.1.2
Works to be undertaken in the next two
months are summarized below:
·
Open trench for mainlaying
and Mainlaying;
·
Jacking pit construction for pipe jacking
·
Trial pit excavation;
·
Formation of piling platform at +89.0mPD;
·
Pipe piling for PAB ELS wall;
·
Site compound set up;
·
ELS works in Portion 3; and
·
Canopy table installation in Portion 3.
7.1.3
Potential environmental impacts arising
from the above construction activities are mainly associated with construction
dust impact, noise impact, water quality impact, waste management and landscape
and visual.
7.2.1
The key environmental mitigation measures
for the Project in the coming reporting period associated with above
construction activities will include:
Dust
·
Regular watering to
reduce dust emissions from exposed site surface;
·
Stockpile of dusty
materials shall be covered entirely by impervious sheeting;
·
Provide vehicles washing
facilities at all site exits to wash away any dusty materials from vehicle
body;
·
NRMM Labels should be
displayed on the applicable equipment on site by the Contractor;
·
All vehicle and plant should
be cleaned before they leave a construction site.
Noise
·
Only well-maintained
plant should be operated on-site, and plant should be maintained regularly
during the construction programme;
·
Quality Powered
Mechanical Equipment (QPME) should be adopted as far as possible.
Water Quality
·
No effluent discharge
would be allowed before the effluent discharge license is acquired.
·
Surface run-off from
construction sites should be discharged into dedicated discharge point via
adequately designed sand/ silt removal facilities;
·
Channels/ earth bunds/
sandbags barriers should be provided on site to properly direct stormwater to
silt removal facilities;
·
Silt removal facilities,
channels and manholes should be maintained, and the deposited silt and grit
should be removed regularly;
·
Open stockpiles of
construction materials on sites should be covered with tarpaulin or similar
fabric during rainstorms;
·
Perimeter channels should
be provided on site boundaries where necessary to intercept stormwater run-off
from outside the site so that it will not wash across the site.
Waste Management
·
Provision of sufficient
waste disposal points and regular collection of waste;
·
Regular cleaning and
maintenance programme for drainage system;
·
Chemical containers shall
be stored with drip tray underneath;
·
Storage, handling,
transport, and disposal of chemical waste should be arranged in accordance with
the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes
published by EPD, and collected by a licensed chemical waste collector.
Ecology
·
Minimize loss of habitats
and associated wildlife;
·
Using directional
lighting to prevent excessive light spill into adjacent natural habitat and
disturbance to nocturnal fauna.
Landscape and
Visual
·
Adequate tree protection
measures shall be provided for the trees to be retained on site.
8.1.1
This is the 4th
Monthly EM&A Report presents the EM&A works during the reporting period
from 1 July 2023 to 31 July 2023 in accordance with the EM&A Manual.
8.1.2
No Action Level or Limit Level exceedance was
recorded for 1-hour TSP monitoring in the reporting period.
8.1.3
No Action Level or Limit Level exceedance was
recorded for construction noise monitoring in the reporting period.
8.1.4
Environmental site inspections
were conducted on 7, 12, 21 and 26 July 2023 by the ET in the reporting period.
8.1.5
No environmental complaint was received in the
reporting period.
8.1.6
No notification of summons and prosecution was
received in the reporting period.
8.1.7
The ET will keep track on the construction works to
confirm compliance of environmental requirements and the proper implementation
of all necessary mitigation measures.
8.1.8
No change to the EM&A programme was made in
this reporting period.
8.2.1
The proposed mitigation measures were properly implemented and were
considered effective and efficient in pollution control.
8.2.2
The ET had no recommendation following the completion of EM&A in the
reporting period.